2019: Second Niger Bridge 44.6% Completed – FG

Follow us on Social Media

Social sharing

The Second Niger Bridge is almost half completed, Federal Controller of Works in Anambra State Innocent Alumonah has said.

The bridge links the West and East stretching from Asaba in Delta State to Onitsha in Anambra State.

Alumonah said the contracting firm, Julius Berger Nig. Plc, had accomplished about 85 piles of 914 millimeter in diameter in different axis.

“The contract was split into phases. Phases 1 to phase 3 have been successfully accomplished and we are now on early works in phase 4. Part of this early works phase 4 forms part of the main contract.

“So far, the 1.2-kilometre sand filling of the road at the Asaba end has reached the height of 2.2 meters out of the expected five meters.

“At the Onitsha end, we have done a lot of sand filling of embankments to a reasonable stage. We have done a lot of culverts as well.

“In all, we have achieved around 44.6 per cent of phase of early work stage 4,” Alumonah said.

He said the contract for the early work stage four was awarded in October 2016 and work commenced in November 2017.

According to him, an advance payment of N2.166 billion was made to the contractor out of the contract sum of N14.466 billion for the early work phase four.

READ ALSO  El-Rufai In Trouble As Lawmakers Set Up Committee To Probe Him

Alumonah said the early work stage four project had a life span of nine months starting from November 2017 to July 2018, noting that there would not be any interruption between stage four and the main contract.

He said the Second Niger Bridge was no longer a political issue as President Muhammadu Buhari had demonstrated commitment to realising the completion of the project.

“The bridge is a link road to all parts of the country not just the South East. It is not a bridge only for the southern part of the country. It is for all Nigerians,” he said.

The controller noted that the continuous maintenance of the existing Niger Bridge built in 1965 was a demonstration of the Federal Government’s commitment.

He said the stress on the existing bridge compelled the Federal Government to build a second Niger Bridge.

He added that the issue of compensation of the affected people had been handled by the Federal Government to a reasonable level and had paved way for work at kilometres 23 to 31.

Alumonah assured Nigerians that the main bridge would not take long to be actualised after the early stage four was completed by July.

Leave your comment on this post

THE ROTTEN FISH: CAN OF WORMS OPENED OF APC & TINUBU'S GOVERNMENT OVER NIGERIA'S ECONOMIC DOWNTURN

WATCH THE CRITICAL ANALYSIS AND KNOW THE RESPONSIBLE PARTIES TO BLAME FOR NIGERIA'S ECONOMIC CHALLENGES, WHILE CITIZENS ENDURE SEVERE HARDSHIPS.
READ ALSO  Retired Colonel Hassan Stan-Labo Is Dead

Watch this episode of ISSUES IN THE NEWS on 9News Nigeria featuring Peter Obi's Special Adviser, Dr Katch Ononuju, 9News Nigeria Publisher, Obinna Ejianya and Tinubu Support Group Leader, McHezekiah Eherechi

The economic crisis and hardship in Nigeria are parts of the discussion.


Watch, leave your comments, and share to create more awareness on this issue.


#9NewsNigeria #Nigeria #issuesInTheNews #politics #tinubu THE ROTTEN FISH: CAN OF WORMS OPENED ...
DON'T FORGET TO SUBSCRIBE AND LEAVE YOUR COMMENTS FOR SUBSEQUENT UPDATES
#9newsnigeria #economia #economy #nigeria #government @9newsng
www.9newsng.com

Leave your comment

Click on the link below or Scan the QR Code to join the 9News Nigeria WhatsApp Channel

9News Nigeria Investigative Reports WhatsApp Channel
9News Nigeria Investigative Reports WhatsApp Channel
About Wisdom Nwedene 11581 Articles
Wisdom Nwedene studied English Language at Ebonyi State University. He is a writer, an editor and has equally interviewed many top Nigerian Politicians and celebrities. For publication of your articles, press statements, contact him via email: nwedenewisdom@gmail.com

Be the first to comment

Leave a Reply